| dc.contributor.advisor | Apriliani, Fany | |
| dc.contributor.author | Ridwan, Muhammad Ariza | |
| dc.date.accessioned | 2025-06-21T02:21:08Z | |
| dc.date.available | 2025-06-21T02:21:08Z | |
| dc.date.issued | 2025 | |
| dc.identifier.uri | http://repository.ipb.ac.id/handle/123456789/162649 | |
| dc.description.abstract | Proses penggilingan bahan baku merupakan salah satu proses penting dalam
produksi semen. Mesin Vertical Roller Mill (VRM) adalah mesin utama dalam proses
penggilingan bahan baku, sehingga perawatan yang tepat perlu dilakukan untuk
menjaga ketersediaan dan produktivitas mesin. Kegiatan preventive maintenance
dilakukan selama dua minggu sekali oleh perusahaan setelah sebelumnya
menentukan komponen yang akan dilakukan perawatan berdasarkan pantauan
lapangan. Untuk itu metode Reliability Centered Maintenance dan perhitungan
keandalan dipilih dengan tujuan dapat mengoptimalkan kegiatan preventive
maintenance, dengan mengidentifikasi setiap risiko kegagalan yang mungkin terjadi
pada equipment 364-RM1 VRM, serta melakukan perhitungan MTBF dan MTTR
komponennya. Sehingga nantinya dapat memudahkan pemilihan tindakan perawatan
dan mengetahui interval waktu perbaikan komponen mesin yang ideal, sesuai dengan
hasil perhitungan keandalan mesin. | |
| dc.description.abstract | Raw material grinding process is one of the important processes in cement
production. Vertical Roller Mill (VRM) is the main equipment in raw
material grinding process, thus proper maintenance needs to be done to maintain
equipment availability and productivity. Preventive maintenance activities are carried
out every two weeks by the company after previously determining the components to
be maintained based on observations in the field. For this reason, Reliability Centered
Maintenance method and equipment's reliability calculations were chosen with the
aim of optimizing preventive maintenance activities, by identifying any risk of failure
that might occur in equipment 364-RM1 VRM, and calculate the MTBF and MTTR
value of its components. So that later it can facilitate the selection of maintenance
actions and find out the ideal machine component repair time interval, according to
the results of the calculation of equipment's reliability. | |
| dc.description.sponsorship | | |
| dc.language.iso | id | |
| dc.publisher | IPB University | id |
| dc.title | Optimasi Preventive Maintenance Equipment 364-RM1 VRM di PT XYZ | id |
| dc.title.alternative | | |
| dc.type | Tugas Akhir | |
| dc.subject.keyword | Failure Mode and Effect Analysis (FMEA) | id |
| dc.subject.keyword | MTTR | id |
| dc.subject.keyword | MTBF | id |
| dc.subject.keyword | Reliability Centered Maintenance (RCM) | id |