Please use this identifier to cite or link to this item:
http://repository.ipb.ac.id/handle/123456789/78481| Title: | Analisis Kinerja Waktu dan Pemodelan 3D menggunakan Software Tekla Structures17 Pada Proyek Pabrik Astra Honda Motor, Cikampek. |
| Authors: | Raimadoya, Machmud Arifin Rahayu, Risda Gustriani |
| Issue Date: | 2015 |
| Publisher: | IPB (Bogor Agricultural University) |
| Abstract: | In general, the construction project has an implementation plan and specific implementation schedule. However, along with the times, the level of difficulty to manage and run the project higher. Construction project management is planning, organizing, directing and controlling resources to achieve short-term goals that have been determined. The research, conducted in March-May 2015 is located in the industrial area of Bukit Indah City, Cikampek, Karawang. Time performance analysis on the development of Astra Honda Motor factory using critical path method is done with the help of Microsoft Project 2013 program. With some additional information that is required, 3D modeling is done based on the Detail Engineering Design data of plant development project Astra Honda Motor. Then the time performance is analyzed using the task manager at Tekla Structure 17 in the form of barchart. Analysis of the S curve construction November to April in the above it can be seen that the resulting zero deviation. Deviation of zero is the desired target by the contractor. As one of the problems that occur include delays in development caused by erratic weather, lack of manpower, and financially. |
| URI: | http://repository.ipb.ac.id/handle/123456789/78481 |
| Appears in Collections: | UT - Civil and Environmental Engineering |
Files in This Item:
| File | Size | Format | |
|---|---|---|---|
| F15rgr.pdf Restricted Access | 3.62 MB | Adobe PDF | View/Open |
Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.