| dc.contributor.advisor | Sukria, Heri Ahmad | |
| dc.contributor.advisor | Barkah, Nisa Nurmilati | |
| dc.contributor.author | FAUZININGSIH, ELITA | |
| dc.date.accessioned | 2025-08-28T13:14:35Z | |
| dc.date.available | 2025-08-28T13:14:35Z | |
| dc.date.issued | 2025 | |
| dc.identifier.uri | http://repository.ipb.ac.id/handle/123456789/170857 | |
| dc.description.abstract | Penelitian ini bertujuan untuk mengevaluasi kinerja proses serta memetakan Value Stream Mapping (VSM) produksi pakan pelet pada Edu-Feedmill. Evaluasi kinerja proses produksi dilakukan melalui perhitungan utilisasi dan efisiensi proses produksi pakan pelet pada Edu-Feedmill. Kemudian dilakukan analisis VSM sebagai tools pada lean manufacturing yang mengidentifikasi pemborosan berikut penyebab permasalahan melalui current dan future state map. Kapasitas produksi pakan pelet pada Edu-Feedmill secara keseluruhan masih rendah dilihat dari nilai efisiensi dan utilisasi yang masih rendah di bawah 80%. Total lead time sebelum perbaikan adalah 28025 detik sedangkan setelah perbaikan total lead time setelah 24458 detik. Analisis pemborosan menunjukkan besarnya persentase aktivitas tidak bernilai tambah 14,29%. Penelitian ini dapat disimpulkan bahwa upaya dari perbaikan proses produksi pakan pelet pada Edu-Feedmill dengan pendekatan VSM meningkatkan perbaikan Process Efficiency Cycle (PEC) sebesar 8,34%. | |
| dc.description.abstract | This study aims to evaluate process performance and map the Value Stream Mapping (VSM) of pellet feed production at Edu-Feedmill. Process performance evaluation is carried out by calculating the utilization and efficiency of the pellet feed production process at Edu-Feedmill. Then, VSM analysis is performed as a lean
manufacturing tool that identifies waste and the causes of problems through current and future state maps. The overall pellet feed production capacity at Edu-Feedmill is still low, as indicated by the efficiency and utilization values, which are below 80%. The total lead time before improvement was 28,025 seconds, while the total lead time after improvement was 24,458 seconds. The waste analysis showed that the percentage of non-value-added activities was 14.29%. This study concludes that efforts to improve the pellet feed production process at Edu-Feedmill using the VSM approach increased the Process Efficiency Cycle (PEC) by 8.34%. | |
| dc.description.sponsorship | | |
| dc.language.iso | id | |
| dc.publisher | IPB University | id |
| dc.title | Efisiensi dan Utilisasi Proses Produksi Pakan Pelet pada Edu-Feedmill dengan Pendekatan Value Stream Mapping | id |
| dc.title.alternative | Efficiency and Utilization of Pellet Feed Production Processes at Edu-Feedmill Using a Value Stream Mapping Approach | |
| dc.type | Skripsi | |
| dc.subject.keyword | Lead Time | id |
| dc.subject.keyword | Lean Manufacturing | id |
| dc.subject.keyword | Pemborosan | id |
| dc.subject.keyword | Value Stream Mapping | id |